Our office will close at 4:30pm on Friday 20th December and reopen Thursday 2nd January 9am.

Get in touch

Get in touch

Get in touch

Thanks for getting in touch.
We'll get back to you shortly.

Need an urgent response?

Case Study

Royal Artillery Barracks

Woolwich, London
The original Woolwich Barracks was built in 1776 and was in constant use as the Royal Artillery (RA) Headquarters until the departure of 16 Regiment RA in July 2007. The history and lineage of this Grade II listed site in the Royal Borough of Greenwich play a big part in its regeneration.
Services provided
The original Woolwich Barracks was built in 1776 and was in constant use as the Royal Artillery (RA) Headquarters until the departure of 16 Regiment RA in July 2007. The history and lineage of this Grade II listed site in the Royal Borough of Greenwich play a big part in its regeneration.

Project Slam

TRC was employed by Lend Lease Construction for the Ministry of Defence ‘Single Living Accommodation Modernisation’ project, also known as Project Slam, one of the largest new-build and refurbishment projects in the UK.

window refurbishment woolwich barracks

Principle Issues

With the works being within a secure site, and with the sensitive retention and protection of retained structural and architectural features to consider, the requirement for unobtrusive, top-rated, thermally efficient secondary glazing that would meet Counter Terrorist Measures (CTM) specification was critical.

It was important to consider a number of designs and specifications in order to provide optimum thermal efficiency, while still providing essential ventilation where necessary, and delivering a frame solution that would play an integral part with the existing traditional box sash windows in addition to the barracks architectural heritage. The importance of furnishing the barracks living quarters with a discreet system that would comply with CTM criteria was a further requirement of the client, and needed to be integrated into the final design.

Once works were completed, this allowed Granada Secondary Glazing to provide a high-specification solution. It used a bespoke heritage window tilting balanced vertical slider with 6.8mm Class A laminated glass in order to achieve high levels of thermal efficiency, largely for the troops’ comfort and well-being, but essentially ensuring their safety and security by complying with the CTM for Normal Risk levels.

Custom-made units reflected the lines of the original windows and were designed to have a minimal visual impact on the character and design of the original building, internally and externally.

Another benefit was further improvement to the acoustic performance of the existing windows, which reduced noise levels in the living quarters, and delivered a more comfortable environment.

Phase 3

Work carried out in the Officers’ Mess. TRC supplied and fitted 50 new timber sliding sash windows and timber casement windows.

Client Ministry of Defence
Principal Contractor Lend Lease Construction
Contract Period December 2013 to July 2015 (Phases 1 and 2)

Phase 3 began February 2016
Contract Value Phase 1: £250,000

Phase 2: £210,000

Phase 3: £60,000

More case studies

All case studies

Get in touch

Get in touch

Get in touch

x
Close

Fill in form to download